Southern
highway land costs soar
Charges of political favouritism
By Lenin Amarawickrama
Construction work has resumed on the long-delayed
southern expressway whose costs have soared with compensation for
land acquisition increasing by as much as six times the original
allocation amid growing complaints by residents of unfair valuations.
The
Rs 33-billion donor funded project was launched in April 2003 is
now over six months behind scheduled after work was disrupted following
the political crises late last year.
Construction
is being carried out by the Japanese firm, Kumagai Gumi, and its
Sri Lankan sub-contractors, Maga and ICC. A recent visit to the
construction site by a team from The Sunday Times FT revealed that
some of the underpasses have already been built and work is underway
on culverts, metal underpasses, and other specialised sections.
Nearly 2000 workers are working on the road along with 40 Japanese
experts.
Government
officials said budgetary allocations for land acquisition had skyrocketed
since the Road Development Authority first drew up plans for the
project in 1990.
The
government had allocated Rs 750 million for compensation in land
acquisition and settlement according to the market values estimated
by the Valuation Department at that time.
As
the project got delayed and land market values rose sharply, the
RDA was compelled to increase the compensation programme several
times. The initial compensation allocation of Rs 750 million in
1990 became Rs 2.2 billion in 2000 and has now risen to Rs 4.5 billion
adding to the financial burden of the government.
The
RDA has identified 5,700 plots of land along the construction path.
Problems have arisen because of substantial differences in the values
of adjacent plots of land. Residents complain that politics influenced
the allocation of compensation for land acquired under the projects
with those with influence being able to get higher compensation
than others.
One
resident, Nandadasa Hatharasingha of Komaladeniya, said that the
value of his land had been underestimated when compared to that
of the adjacent plot. A priest in the area, Ven. Kalubovitiyana
Wimalarathana Thera of the Sri Salabhodhirajarama temple in Baddegama,
also complained of inadequate compensation.
The
highway will cut across his half built temple and he is demanding
at least Rs 1 million to be relocated. The government has offered
him only Rs 250,000 as compensation. |