Southern
highway
Zigzag road to the South
The Joint Organization of the Affected Communities on Colombo-Matara
Highway, referring to a report in The Sunday Times FT on October
31 on the southern highway, said in a statement last week that there
is a lot of corruption taking place in this project.
Sarath
Athukorale and Heather Mundy from the civil society group accused
some officials in the Road Development Authority (RDA) of using
this project to achieve their own ends.
Excerpts
of the statement:
In 1999 the ADB offered the government a loan to build
a two lane, (later increased to four lanes) highway of 128 km from
Matara to Colombo (actually Kottawa). The design was by International
Designers Wilbur Smith Associates who altered the RDA design by
18 km in the north and 30 km in the south. These changes were to
minimize housing loss and to make the expressway viable by taking
it closer to traffic sources.
This
improved trace was called the CT (Combined Trace) and was accepted
by the RDA. It was estimated to cost Rs.15 billion. The northern
deviation was done to give direct connection to the Galle Road close
to Panadura while the southern deviation brought it close to Galle
and the Port. Both these deviations ran through abandoned paddy
fields.
The
CEA in giving permission for the project were asked to change the
trace and used the excuse of the recreational area of the Bolgoda
Wetlands near Moratuwa to alter the northern deviation.
Your
article said government officials blamed rising land costs for the
increase in compensation. But this is not the real cause. The increase
is due to two reasons. With the change of trace done by the RDA
more than double the number of people are losing their homes. In
addition instead of running through abandoned paddy fields it runs
through residential property and productive paddy fields and estate
lands. Therefore compensation is vastly more on the Final Trace
(FT). The designers' trace which incurred minimal compensation costs
is now totally abandoned and the government has to bear this huge
cost.
Because
they have chosen to go through villages the RDA has to build many
more over/under passes to preserve the social structure of the village.
The total cost has gone up to Rs 33 billion. Currency devaluation
since the loan documentation calculated at Rs 72 to the dollar would
have taken the maximum cost of Rs 15 billion to Rs. 21.5 billion.
Where has the other Rs.11.5 billion gone? Certainly not to the resettled
people who are living in abject poverty as highlighted in the press.
The
Sunday Times report says that the cost of the compensation is now
estimated as Rs.4.5 billion In the October 2002 Resettlement Plan,
the RDA estimate was Rs. 2.9 billion. For the same number of properties
in two years the figure has nearly doubled. How can this enormous
difference be explained? In any case the resettlement plan says
that it had a detailed inventory of losses. Looking at the poverty
created in the resettlement sites it can only be concluded that
somebody other than the resettled people is getting the money.
The
government must carry out a transparent investigation of this project.
Transferring the Project Director and sitting back is not the way
to be accountable for public money.
Any
government has limited resources. While the government allows the
RDA to do what they want with no control of purpose or spending
they will not have any money available for health care, education,
drought relief, rural industrial development, subsidising the effects
of rocketing oil prices etc., etc.
The
media and the few who are aware of these facts owe a duty as patriotic
citizens to inform the public that their money is being wasted.
Response
Southern highway will reduce travel time, cost, accidents
In a detailed response to the citizens' group, Alessandro Pio, Country
Director the Asian Development Bank (ADB) said:
We
would like to comment on the increased costs of land acquisition
and resettlement under the project, which have indeed exceeded original
estimates.
This
is due to significantly higher land and asset valuations than originally
expected, based on the principle that replacement value is used
as a basis for determining compensation amounts instead of the traditional
method of depreciated value, and the implementation of a more complete
compensation package compared to previous road projects. The increase
also reflects the rapid increases in land prices generally in the
south of the country, some of it ironically a consequence of the
government's commitment to build the southern highway. Both of these
factors are far more significant in the final land and asset acquisition
cost than the relatively marginal increase due to unavoidable modifications
to the highway's alignment.
That
said, the alignment modifications have definitely added to the acquisition
costs, although they have not changed the major component of the
project's cost (the construction of the highway itself represents
more than 80% of the total cost). The additional land costs became
unavoidable when the Central Environmental Authority required that
the highway's alignment be adjusted to avoid wetlands in two sensitive
areas and reduce the impact on the urban areas around Galle.
As
a result, during the project's detailed design many adjustments
were made, some large and others small, in close consultation with
communities who came within the project's adjusted alignment, although
not all communities wished to participate in this process.
The
objective was to develop a highway that carefully balanced country,
community and economic benefits against financial, social, and environmental
costs. Your readers will appreciate that for a project of such magnitude
this is a challenging task, requiring skilled study and assessment
of many factors, including environmental impacts, technical considerations
such as traffic flows, terrain and soil conditions, economic and
cost considerations, road safety, and social impacts, including
resettlement, community separation, noise, and many more.
The
outcome has been an alignment that maximizes benefits while minimizing
social and financial costs. It is definitely correct that more houses
are now affected compared to when the project was conceived, an
unavoidable consequence of the efforts to avoid the important wetland
and urban areas. The increase in affected houses has been kept to
the minimum possible through careful technical design and extensive
consultation with communities who could be affected as the modified
alignment was being developed and fine-tuned.
As
mentioned earlier, the higher cost of land acquisition and resettlement,
however, represents only a fraction of the total project cost about
which there seems to be considerable confusion. At the time the
project was approved by the ADB's Board of Directors in November
1999, the total cost was estimated at about $300 million, equivalent
to Rs 21 billion at the exchange rate at the time. Depreciation
of the rupee alone would bring that amount to approximately Rs 30
billion today. With this cost the project's economic rate of return
was 14.5%, comfortably above the usually-accepted cut-off value
of 12%. Construction costs have increased, although not significantly
and definitely not as a consequence of alignment modifications,
but benefits have likewise increased, so the overall economic viability
of the project remains intact.
We've
also heard from time to time that modifications to the alignment
have moved the highway far away from traffic centres thus affecting
its viability. This is simply not so. The basic network structure
hasn't changed, and the final alignment is at the most within a
few km of the earlier alignment. The increased travel distances
for vehicles joining the highway are so small, relative to the vastly
reduced travel times on the highway compared with the existing Galle
Road, that the impact on viability, if any, would be negligible.
In
fact, for Galle, the addition of a purpose built access to the city,
which was not included in the original design, will significantly
improve access and reduce travel time, and dramatically reduce noise
and traffic impacts for the Galle community.
By
their nature, large scale and complex projects such as the Southern
Highway inevitably run into problems of various kinds during implementation.
It is important to detect and address these problems promptly, and
civil society and the press can play an important role in helping
to identify these shortcomings.
While
expressing concerns about costs and problems, however, one must
not forget the benefits of the project. When completed, the expressway
will reduce travel time, cost and accidents and contribute to increasing
employment and incomes in the southern part of the country by promoting
agriculture diversification, reductions in post-harvest losses in
agriculture and fisheries, and increased tourism flows, ultimately
contributing to the area's economic development and poverty reduction.
Business
Editor's note: The RDA was also asked for a response to the allegations
from the citizen's group but there was no reply. |