A
big kill from Navy big guns
President Chandrika Bandaranaike Kumaratunga on Wednesday told armed
forces chiefs the Government would not allow any fresh military
procurement with immediate effect. Only the ongoing deals for which
orders have been placed would be permitted in view of financial
constraints. Long term needs, she said, would have to be prioritized
for consideration later.
The
three Commanders – Lt. Gen. Shantha Kottegoda (Army), Vice
Admiral Daya Sandagiri (Navy) and Air Marshal Donald Perera (Air
Force) met her at Janadipathi Mandiraya with their staff dealing
with procurement matters. This was to review issues relating to
armed forces procurements in the light of mounting projected needs
and severe financial constraints in meeting all of them.
The
Army, the largest among the security forces, had mainly focused
on recurring expenditure. So has the Sri Lanka Air Force although
the Tiger guerrilla acquisition of air capability had necessitated
them to request for equipment needed for counter measures. But the
Navy’s requirements, which even stunned the Government’s
own Procurement Committee, have run into billions of dollars or
rupees.
According
to evidence that has unfolded before this Committee chaired by a
former Defence Secretary, Chandrananda de Silva, some of the recommendations
for procurement by the Navy have been made without any proper assessment
of needs. Nor have such needs been weighed against the financial
resources available, their suitability in terms of the existing
Naval assets or its economic viability.
One
such instance that clearly highlighted these serious shortcomings
was the recommendation by the Chief of Defence Staff and Commander
of the Navy, Vice Admiral Daya Sandagiri, to procure the British
built logistics landing ship Sir Gallahad. This was repeatedly highlighted
in The Sunday Times (Situation Report) in the past weeks. There
were many other similar requests by the Navy that went before the
Government. They highlight the scandalous state of affairs with
regard to procurements. Here is another glaring example:
In
1997 the Navy purchased from Britain’s Royal Ordnance ten
30 mm Oerlikon (GCM-A/A32) guns at a cost of over Rs 703. 9 million.
This is a gun used both for air defence and in surface to surface
warfare. Nine units were installed on ships and one was allocated
for training purposes at the gun site located at Eastern Naval Area
Headquarters in Trincomalee. They were regularly rendered non operational
due to frequent failures particularly in the HPTU or Hydraulic Power
Transmission Unit. A ding dong battle continues to date between
the Royal Ordnance and the Navy over this matter. As revealed below,
documents in possession of The Sunday Times confirm this and bare
many irregularities.
Notwithstanding
this, the same supplier was to be awarded the contract after the
Navy called for tenders in the year 2000 for the procurement of
two guns with Fire Control Systems (FCS). This was for installation
in SLNS Sayura, the former Indian Navy Offshore Patrol Vessel (OPV)
INS Saryu. The gun (30 mm GCM- A/A32) was to come from the Royal
Ordnance in Britain whilst an accompanying Fire Control System was
to be obtained from Radamec Defence System also from the same country.
The Fire Control System or FCS is a device that automatically detects
(with the use of sensors etc) a target and directs fire at it. The
total cost was to be Sterling Pounds 3,762,093 or over Rs 658,366,100.
(Converted @ Rs 175 to a UK Sterling Pound).
The
reason for the selection – Britain’s Royal Ordnance
was the only supplier that met with the Navy’s requirement
that the gun in question should fire 800 or more rounds per minute.
Compared to other purchases, this benchmark left out almost all
other would be suppliers. The tender had stipulated that the gun
required was between 30 mm and 40 mm. There was no other supplier
who could meet with the specifications to provide a gun that fired
more than 800 rounds per minute. Moreover, Vice Admiral Sandagiri
declared that this procurement was very urgently needed. Hence he
did not want to lose any time.
Yet,
a Technical Evaluation Committee (TEC) headed by Rear Admiral Vasantha
Tennekoon examined this procurement but did not favour its purchase.
It recommended that fresh tenders be called in view of the inability
of the company to ensure the previously sold ten guns were in working
order. The heavily priced guns were defective. In other words the
TEC was not happy with the past performance of Royal Ordnance guns.
But, Navy Commander, Vice Admiral Sandagiri wanted to procure the
two weapons on the grounds that fresh tenders would further delay
equipping SLNS Sayura.
He
recommended this procurement first to the then United National Front
(UNF) Government. A three member Cabinet Appointed Tender Board
(CATB) led by Dhara Wijetilleke, Secretary, Ministry of Justice,
Austin Fernando, Secretary, Ministry of Defence and S.B. Divaratne,
Deputy Secretary to the Treasury studied the matter. The CATB on
June 3, 2002 directed that that the Technical Evaluation Committee
submits a report to them “on completion of trial test with
regard to entire satisfaction of technical performance of both guns
and the fire control system, especially HPT unit of the gun system
for re-consideration.”The
CATB warned that no financial commitment is made by the Navy against
proposed trial tests.
Later,
Vice Admiral Sandagiri obtained the approval of then Defence Minister,
Tilak Marapana. However, Mr. Marapana had second thoughts and made
sure that the deal did not go through. The Sunday Times learnt he
was told by those in the know of the pitfalls if the purchase was
allowed. But Vice Admiral Sandagiri did not give up his efforts
though he was fully in the know the guns supplied earlier were clearly
defective. Soon after the UPFA Government was voted to power, he
revived efforts.
On April 11, 2003 he sent a two-page fax to the Royal Ordnance (part
of British Aerospace) in Britain titled “WARRANTY REPAIRS
TO GCM 30 MM GUN HPT UNITS.” This is what he said:
“1.
It is re-capitulated that the SLN purchased ten 30 mm GCM guns from
Royal Ordnance at a cost of Rs 703,923,230.00. From the date of
installation, 04 April 1997 it was noted that the trigger unit of
this gun has an inherent problem due to which it is not possible
to operate the gun at their optimum efficiency.
“2.
Your esteemed organisation provided support by placing an engineer
in Sri Lanka, on call for two years, whereby any defects were attended
by him very quickly. Further you had made a commitment to change
the trigger units at the first opportunity. In fact you had made
an undertaking in writing that the units will be replaced by a more
efficient electro-mechanical unit in the year 2000. In the meantime
your representative here was also recalled in August 2000.
Since
then a deaf ear has been turned towards the many pleas that the
SLN had made regarding the deficiencies of the units. As of date
there are seven defective guns, which needs urgent attention. “3.
(a) As per reference above at the rate you intend to carry out repairs
a minimum of four months will elapse before you could complete the
repairs starting today during which time SLN is unable to make use
of the guns for which an investment has been made.
“(b)
Further you indicate that replacement of existing trigger units
by a new HPTU will begin only by the end of 2003. “4. It is
informed quite regretfully that SLN has been patiently absorbing
all excuses that have been forwarded by your organisation. However,
instead of improving for the better, it appears that the trends
and attitudes displayed by your organisation has been declining
from bad to worse over the years.
“5.
Hence it is very obligingly informed that it is about time that
a more agreeable method be employed to find a solution to the problem,
which is your own creation, and absolve the SLN from the price it
has to pay for an attitude that is most unbecoming of an organisation
of your founding.
“6. Unless an immediate solution is provided SLN may be reluctantly
compelled to make matters known to the authorities concerned where
reliance cannot be placed on your organisation.
“D.W.K.
Sandagiri, VSV, USP, reds, psc, MSc (DS), FlMgt, Vice Admiral, Commander
of the Navy.” The “trends and attitude” of Royal
Ordnance which Vice Admiral Sandagiri complained “have been
declining from bad to worse” did not change. Yet, he despatched
a four member Navy team (that travelled elsewhere on official business)
to Britain to examine the Royal Ordnance guns and the Radamec Fire
Control System. They visited Britain on December 19 last year and
returned to Colombo in early January, this year.
The
team reported back to Vice Admiral Sandagiri that the defective
HPTU unit in the gun has been rectified by the manufacturers. They
suggested that payment for the two guns to be procured be made only
after (a) the new HPT unit is to the satisfaction of the Navy, and
(b) the HPT units of the existing guns that are defective are replaced
with “new” HPT units.
A Navy team that conducted tests seven years earlier on the same
gun were not happy. One of its members, Rear Admiral Wasantha Karannagoda,
now Commander, Eastern Naval Area headquartered in Trincomalee,
had this to say on March 31, 2001 in a minute in the relevant purchase
file at Navy Headquarters.
“…The
second time also RADAMAC and 30 mm gun have emerged as the winner
but the TEC (Technical Evaluation Committee) is not happy with the
system due to certain drawbacks…..
“I
too agree with the views of the Chairman TEC due to the following:
a. …..a report submitted by a Board of which the present C
of N (Commander of Navy – reference is to Vice Admiral Sandagiri)
was the President. The paragraph 4 a(4) of the report indicate that
the available 30 mm GCM guns have frequent failures.
b.The
biggest problem the 30 mm GCM gun has is the frequent failure of
HPT unit. The manufacturer had tried to correct this problem in
June 2000, but has failed up to now.
c DNL
(Director Electrical and Electronics) has sent a detailed letter
indicating to manufacturer of the problems of the modified HPT unit
of 30 mm GCM guns and to attend to them early, in July 2000 but
they have not even bothered to reply.
Rear
Admiral Karannagoda added: “Under these circumstances going
for 30 mm GCM gun is a waste of money. Therefore any FCS (Fire Control
System) with 30 mm GCM guns is strongly not recommended particularly
in view of defects of the weapon and extremely poor after sales
service…….I was a member of the team that carried out
field trials of RADAMEC Fire Control System in Trincomalee in 1994.
The team rejected the offer ….
“……The Director who handled this at NHQ (Navy
Headquarters) had not shown the report submitted by the team that
carried out trials to C of N. However, at the last minute I was
able to point out the situation to C of N. Subsequently the purchase
was stopped. It is such a strange co-incidence the same company
RADAMEC is getting selected with a bad gun, again and again…..”
Were
the recommendations of this team studied before Vice Admiral Sandagiri
asked a Navy delegation travelling elsewhere to proceed to Britain?
Why were the apprehensions voiced by senior Navy officers ignored
in doing so? What was the need to pursue further procurement from
a supplier who had provided defective guns? Only a formal inquiry
will bring forth answers to these and many other puzzling questions.
Vice Admiral Sandagiri could not clinch the deal during the UNF
regime. The situation became more curious after he pursued his efforts
when the UPFA Government was voted to power. A new Cabinet Appointed
Tender Board was named. It is headed by H.M.G.S. Palihakkara, Foreign
Secretary and comprised Major General (retd.) Asoka Jayawardena,
Defence Secretary and S. B. Divaratne, Deputy Secretary to the Treasury
representing the Secretary. Vice Admiral Sandagiri was in attendance.
They
met at the Defence Ministry on April 7, this year, and considered
a letter addressed to them by Vice Admiral Sandagiri on April 5,
2005 for the supply, installation and commissioning of two medium
calibre Stabilised Guns with Fire Control System. He had recommended
the Royal Ordnance guns and the Radamec Fire Control System and
again stressed on the urgency to procure them.
The
CATB made the following observations:
“(a) CATB at its meeting held on 18-06-01 had directed the
TEC to pursue the gun system offered by the following suppliers
in view of the recommendation made by the Commander of the Navy,
as the earmarked flag ship of SLN “SLNS Sayura” has
been deployed in northern and eastern waters without a proper weapon
outfit.
“1.
M/s Royal Ordnance, UK – the manufacturer of the guns.
“2. M/s Radamec Defence System, UK – the manufacturer
of the fire control system.
(b) Pursuant to the CATB decision on 02-06-02, the Commander/Navy
has negotiated with the two manufacturers and reported in his letter
dated 13.09.2004 that –
i. the defect in the HPT units of the 30 mm GCM gun has been rectified
and is working satisfactory (sic). The defective HPT units of the
existing guns of the SLN ships could now be replaced.
ii.
with regard to trial test of Radamec fire control system, the supplier
proposes that the SLN team visits a country where this system is
available for the purpose of checking the performance in all aspects……….
The CATB noted “that the initial quoted price for the system
was Sterling Pounds 2,632,440. The supplier has now decided to revise
the initial quoted price declaring following contributory factors,
which severely affected the inability to maintain the original quoted
price given in December 2000. (a)
Advancement
of technology in regard to HPT units and fire control systems, and
(b) the inflation. Accordingly, the supplier has now offered a revised
price of Sterling Pounds 3,762,093. The price difference would be
Sterling Pounds 1,129,653 and it is categorically unacceptable.”
The CATB added: “Delay in progressing (sic) the tender since
December 2000 could not be regarded as SLN’s inefficiency.
The delay in rectifying the HPT problem is a liability by the supplier.
While accepting the inability to maintain the initial quoted price
over 2 – 3 years, the CATB decided to inform the Commander
of the Navy that the revised price is considerably high and cannot
be accepted. Therefore, a considerable price reduction is needed
for further consideration of the tender.”
What
did Vice Admiral Sandagiri do following the observations of the
Cabinet Appointed Tender Board? Twenty two days after the CATB meeting,
on April 30, 2005 he sent a fax to Royal Ordnance. He not only invited
a team from the company to come to Sri Lanka but also said it could
be an opportunity that could be utilised to discuss “other
related issues or new products too.” That is with a company
which has reportedly not honoured its commitments. Here is the full
text of his fax message:
“Reference - Commander of the Navy’s letter No. DNL
dated 11th April 2003.
“It
is needless to mention that Sri Lanka Navy spent considerably to
purchase ten 30 mm GCM guns. The weapons have been ineffective since
installation due to recurrent defects in the HPT units. This matter
has been reported regularly and to-date there is no permanent solution
provided.
“a.
Your organisation had initially made an undertaking in writing that
HPTUs will be replaced in the year 2000 and then in 2003 but failed.
Finally, at a presentation made on 6th September 2004 it was mentioned
that HPTUs will be made available in the second quarter of 2005,
for use in SLN.
“b.
It is further noted that BAE (British Aerospace) systems do not
respond to inquiries on spares for the said weapons either.
“Considering the above it is appreciated if any representative
from your organisation could visit Sri Lanka Navy before and brief
on activities intended for the immediate future regarding aspects
at para two above please. The opportunity could be utilised to discuss
any other related issue or new products too.”
Appearing
before the CATB on April 7, 2005, Vice Admiral Sandagiri, in his
efforts to obtain their approval, made clear that the HPT units
of 30 mm GCM gun have been rectified. He said existing defective
HPT units of guns with the Navy could now be replaced. But, neither
has Royal Ordnance replaced these guns nor heeded his request to
send a representative to Sri Lanka to talk with the Navy.
Instead,
a four member team from the Radamac Defence Systems UK arrived in
Colombo. Vice Admiral Sandagiri and five other senior officers met
them on June 15 at a conference at Navy Headquarters. It is to them
that Vice Admiral Sandagiri conveyed the CATB request for a lower
price. A representative of the company said they could make a five
per cent deduction on the total contract. Evidently the supplier
of the Fire Control System was also speaking for the supplier of
the guns.
Vice
Admiral Sandagiri told the Radamac team there was a “mandatory
requirement” to rectify the HPT units of the existing guns.
He could not tell this to Royal Ordnance since no one had arrived
in response to his invitation. He told the Radamec team this was
to be incorporated in the new purchase agreement. As directed by
the CATB, payments would not be made until the rectification is
made, he told the team. That was how Sri Lanka Navy was doing procurement
business. But all their deals including this sordid one have now
been stopped by President Kumaratunga.
In
analysing this deal a number of key issues arise. The first and
most important is why Vice Admiral Sandagiri went on pressing two
successive Governments during a period of five long years to purchase
the two guns from Royal Ordnance on the grounds that this procurement
was so urgent? Could he not have called for fresh tenders and sought
a much more economical weapons system from other suppliers worldwide?
Since the need to procure was on the grounds that it was urgent,
why did he prolong the dialogue only with Royal Ordnance for five
long years? This is when they had not even responded to his representations?
Why
was he insistent for five long years that the procurement be made
only from Royal Ordnance? More so, when they have defaulted on the
ten guns purchased earlier by not ensuring they are in working order.
It is widely known that the cost of the ten weapons was high. Why
were members of the same evaluation team that accepted the guns
sent on inspection missions? Why were no other senior officers who
were not involved in the evaluation called upon to do so thus ensuring
greater transparency? This position is further highlighted in Rear
Admiral Karannagoda’s comments that a Director who handled
a report relating to field trials had not shown it to the Commander.
What
of the ten Royal Ordnance guns now with the Navy in the meanwhile?
A signal sent to Navy Headquarters from then Commander, Eastern
Naval Area, Rear Admiral Sarath Weerasekera on June 23 says it all.
Rear Admiral Weerasekera is now Deputy Chief of Staff at Navy Headquarters
and in this capacity responsible for intelligence, operations, hydrography,
oceanography, plans and projects. He is directly responsible to
the Commander. This is what his message said:
‘PRESENT
STATUS OF 30 MM GCM GUNS HPT UNITS AS FOLLOWS:
“A. Operational – 04 units.
B. Semi operational – 04 units (only burst mode firing possible.
C. Non operational – 05 units.
“Availability of sufficient number of FGBs (Fast Gun Boats)
for operational commitments / deployments severely affected due
to above.
“Request inform principals to attend repairs early or request
concurrence to open HPT units to attend possible repairs.”
Note: Though the number of GCM 30 mm guns with the Navy are ten,
additional HPT units had been obtained. Even they were defective,
as the signal points out.
What
is the consequence of the non availability of fast gun boats equipped
with weapons during a crisis situation? It places the lives of Navy
officers and sailors in great peril. That is when they perform the
sacred duty of defending the nation’s sovereignty and territorial
integrity.
Merely halting procurements on the grounds that there is no money
is not the answer. In the public interest a detailed probe is essential
to ascertain why expensive, unsuitable equipment is being recommended
for purchase.
This
is to prevent the recurrence of malpractices in military procurements.
The answer does not lie in spying on journalists or tracking down
their sources. In the board rooms of the Navy Headquarters, this
was what some top brass were trying to do poring over telephone
bills to ascertain who spoke to whom. That certainly is not the
answer as coming events will strikingly show.
|