ITI
sets up on-site office to assist in road construction
The
Industrial Technology Institute (ITI) has set up its first on-site
office in Sri Lanka – a unit to check noise and vibrations
levels during construction of the Southern Expressway.
Construction
has already begun in the third segment of the Southern Expressway
project with work being carried out in different places of the road
trace. It follows a strict work schedule to ensure the timely completion
of the task, and for cost effectiveness.
“To
carry out the work according to the schedule, ‘on-the-spot’
advice and recommendations on environment-related problems should
be provided at the site. And thus the Electro Technology Centre
(ETC) of ITI as the technical consultative institution on the environmental
effects of noise and vibration, took a step forward and put up its
site office in Baddegama, with two mining engineers and other experts
in related fields, to ensure effective monitoring,” an ITI
statement said.
It
said ITI has been involved in the pre-identification and monitoring
of hazards due to noise and vibration during the last year, and
both the ITI and the project staff felt that an on-site office would
provide for much greater efficiency. This is the first time in Sri
Lanka that environmental factors in a road construction project
are being monitored.
The
Southern Expressway is the second major construction project started
by the Sri Lanka government after the accelerated Mahaweli project.
This expressway runs from Kottawa to Matara. Construction began
in 2003. Construction on the 232km-long expressway has been broken
into three phases – Kottawa to Dodangoda, Dodangoda to Kurudugahahathamme
and Kurudugahahathamme to Matara. The last phase, which is the longest
(60 km), is now in progress.
Usually,
such large-scale construction projects are delayed, or even stalled,
due to various environmental-related problems. The government consequently
runs into huge financial difficulties by having to pay compensation
to the contractor for such delays, thereby incurring expenses over
the estimated value of the project.
“In
order to minimise the delays and obstacles due to environment-related
issues, representatives from the Central Environmental Authority,
safety and environmental groups of the construction companies, and
a technical consultative institution on environment-related activities
are now working as groups. This is a welcome move,” the statement
said.
Noise
and vibration in road construction projects could occur due to several
activities: rock excavation or mining, road compacting using vibrators
and piling operations result in unbearable and unsafe levels of
noise and vibrations causing a severe disturbance to those living
in surrounding areas, and also damages to property.
At
the preliminary stage of the road construction projects, while the
road trace is being identified, the properties that come under the
project site are identified and acquired by the government. While
the actual construction work is going on, the resultant effects
have to be pre-identified to minimise potential problems. The pre-identification
has to be done on a scientific basis in order to minimise the adverse
effect and also to be cost effective.
In
the Southern Expressway project there are five main groups working
together on environmental impact studies. ITI and GSMB Technical
Services as the technical institutions, CEA as the legal and implementing
body, and the environmental and safety team in the Kumagai Gumi
construction company and supervision consultants.
Before
any rock mining activity commences, ITI together with CEA has to
decide on the norms for the activity and identify the possible parties
that could be affected due to the activity. For the affected parties
there are three types of remedial actions that could be taken depending
on the degree of effect, i.e. evacuation, temporary evacuation and
inconvenience payments, followed by damage repairs if necessary.
Based
on the remedial action recommended by ITI, the CEA gives approval
for its implementation, with the concurrent agreement of the affected
parties. During this period, with remedial action being taken and
construction and mining activities still continuing, the ETC team
at the site office collects necessary data, analyzes them and keeps
on refining the norms further while monitoring the implementation
of the norms continuously. Hence, the Southern Expressway project
proceeds with the lowest interruptions and minimal disturbances
to the people who live around the project area.
|