The Moragahakanda hydro-electricity plant, a 25MW hydro-power to the national grid is ready to generate electricty as all the testing has been concluded.
The Electrical engineers say the electricity generation could successfully commence when the water level rises in the reservoirs during the upcoming rainy season.The Moragahakanda hydro-electricity plant built within a shortest period of time.
The Plant was built near the Moragahakanda main dam and the electricity will be generated using four turbines. This will consist of two 7.5 Megawatt Turbines and another two 5 Megawatt Turbines.
The water released after operating turbine machines of 7.5 megawatts, will be taken to Mahakanadara Reservoir through Ihala Elahera cannel. The water released by operating of turbines of 5 megawatts will be sent to Ambanganga and then to Giritale, Minneriya, Kavudulla and Kantale reservoirs through old Elahera cannel.
The Moragahakanda reservoir is situated at 132 meter height from the sea level. When the water level of the reservoir increased to 165 meters from the sea level the power plant will be operated. When it reaches the highest level 185 meters the power will be generated.
You can share this post!
Content
The Ministry of Environment has taken steps to declare an additional 50 forests as protected reserves, Under the ’Wanaspati’ National Programme.
The National Water Supply and Drainage Board (NWSDB) warned that water supply restrictions would be imposed from 8.00pm today in Colombo District from today onwards
The meteorology department issuing a warm weather advisory for today that the temperature felt on human body is likely to increase up to ‘Caution level’ at some places in Western, Sabaragamuwa, Southern, North-western, Northern and North central provinces and in Monaragala district.

Leave Comments